Follow the project – Villa Tamara
Cleaning the grounds
March 2019
Pouring the foundations of the 1st stage
April 2019
The ground floor rises
May 2019
Pouring individual pools
May 2019
Floor of the 2nd floor
June 2019
The 2nd floor rises
July 2019
Creation and compaction of the interior street
July 2019
The roofs
July 2019
The reception
August 2019
Roof finishing
September 2019
VRD and preparation of the beach access road before asphalting
October 2019
Structural work and interior street
January 2020
Beginning of the finishes
March 2020
Finishes common areas and beach access street
June 2020
Delivery Villa Tamara
July 2020